Notified maximum demand (NMD) optimiser

Your notified maximum demand (NMD) is the capacity you reserve on the network, and you pay for it every month whether you use it or not. Set it too high and you pay for idle capacity; too low and exceedances bring excess charges.

Inputs

Pre-filled with an illustrative case. Results update as you type. Jump to results

Monthly maximum demand (kVA)

The last 12 bills, oldest first: the kVA maximum (or chargeable) demand line.

Paste 12 values from a spreadsheet

Your NMD and capacity charges
kVA
R/kVA/month

Distribution plus transmission network capacity charges from your tariff.

R/kVA/month

Enter 0 if your tariff has none.

Recommendation
%
kVA
%

Change in peak demand over the next 12 months.

Exceedance rules
Exceedance rules
%

Exceedances within this margin can be forgiven.

per 12 months

Results

Recommended NMD 970 kVA, saving about R97k a year against the current 1,200 kVA.

Recommended NMD
970kVA
Peak 915 kVA + 5.0% headroom
Annual saving
R97k
Capacity and excess charges, 12 months
Current headroom
24%
Current NMD 1,200 kVA
Exceedance risk
Low
About 9% a year at the recommended NMD

CheckThe current NMD is 24% above the highest month: capacity you pay for every month but do not use.

Monthly maximum demand against the NMD

kVA by month, oldest first. Hover a column for its value.

  • Maximum demand
  • Current NMD
  • Recommended NMD
020040060080010001200Month 1: 742 kVA1Month 2: 760 kVA2Month 3: 781 kVA3Month 4: 805 kVA4Month 5: 868 kVA5Month 6: 902 kVA6Month 7: 915 kVA7Month 8: 897 kVA8Month 9: 836 kVA9Month 10: 790 kVA10Month 11: 768 kVA11Month 12: 751 kVA121,200 kVA970 kVA

Current against recommended

Next 12 months, using the demands above. Capacity charges are billed on the annual utilised capacity.

MeasureCurrentRecommended
NMD1,200 kVA970 kVA
Annual utilised capacity1,200 kVA970 kVA
Capacity chargesR504,000R407,400
Excess chargesR0R0
TotalR504,000R407,400
Months above the NMD00
Chance of an exceedance in 12 months0%9%

Annual cost by NMD

Capacity plus excess charges for 12 months at each possible NMD. Below the peak you still pay for the peak (annual utilised capacity), plus any excess charges; above it, every extra kVA costs the full rate.

R0R100kR200kR300kR400kR500kR600k7307808308809309801,0301,0801,1301,1801,260RecommendedCurrentNMD (kVA)
Show the numbers
NMDCapacityExcessTotal
730 kVAR384,300R175,750R560,050
740 kVAR384,300R157,000R541,300
750 kVAR384,300R116,375R500,675
760 kVAR384,300R79,575R463,875
770 kVAR384,300R73,275R457,575
780 kVAR384,300R65,025R449,325
790 kVAR384,300R45,075R429,375
800 kVAR384,300R34,675R418,975
810 kVAR384,300R22,625R406,925
820 kVAR384,300R20,125R404,425
830 kVAR384,300R16,675R400,975
840 kVAR384,300R14,425R398,725
850 kVAR384,300R12,175R396,475
860 kVAR384,300R7,825R392,125
870 kVAR384,300R2,250R386,550
880 kVAR384,300R1,275R385,575
890 kVAR384,300R525R384,825
900 kVAR384,300–R384,300
910 kVAR384,300–R384,300
920 kVAR386,400–R386,400
930 kVAR390,600–R390,600
940 kVAR394,800–R394,800
950 kVAR399,000–R399,000
960 kVAR403,200–R403,200
970 kVAR407,400–R407,400
980 kVAR411,600–R411,600
990 kVAR415,800–R415,800
1,000 kVAR420,000–R420,000
1,010 kVAR424,200–R424,200
1,020 kVAR428,400–R428,400
1,030 kVAR432,600–R432,600
1,040 kVAR436,800–R436,800
1,050 kVAR441,000–R441,000
1,060 kVAR445,200–R445,200
1,070 kVAR449,400–R449,400
1,080 kVAR453,600–R453,600
1,090 kVAR457,800–R457,800
1,100 kVAR462,000–R462,000
1,110 kVAR466,200–R466,200
1,120 kVAR470,400–R470,400
1,130 kVAR474,600–R474,600
1,140 kVAR478,800–R478,800
1,150 kVAR483,000–R483,000
1,160 kVAR487,200–R487,200
1,170 kVAR491,400–R491,400
1,180 kVAR495,600–R495,600
1,190 kVAR499,800–R499,800
1,200 kVAR504,000–R504,000
1,210 kVAR508,200–R508,200
1,220 kVAR512,400–R512,400
1,230 kVAR516,600–R516,600
1,240 kVAR520,800–R520,800
1,250 kVAR525,000–R525,000
1,260 kVAR529,200–R529,200

Add to a business case

What is this?

Save this result as one measure in a project kept in this browser, then combine it with results from other tools for payback, NPV, IRR and a cost curve.

Saving, year 1
R96,600/yrAssumed

Every input above is still the illustrative example, so the result is tagged assumed. Enter your own numbers to make it yours.

Assumed
R

An NMD change needs no equipment; enter any utility fee or consultant cost. Default R0.

Assumed
years

Years the lower NMD holds before load growth needs a new one. Default 5.

Assumed
R/yr

Usually none. Default R0.

Method

Recommended NMD
NMD* = ceil_step( max_m MD_m × (1 + growth) × (1 + headroom) )
Annual utilised capacity
AUC = max( NMD, max_m MD_m )
Eskom's definition: the higher of the NMD and the highest demand in a rolling 12 months.
Capacity charges for 12 months
C = AUC × (c_network + c_generation) × 12
Excess charge for the n-th exceedance
E_n = n × (MD − NMD) × c_network (first 2 exceedances within 5% of the NMD forgiven)
Our reading of the Eskom NMD rules: the count multiplies the charge, so repeated exceedances escalate.
Annual saving
S = (C + ΣE) at current NMD − (C + ΣE) at NMD*
Exceedance risk (indicator)
p_month = 1 − Φ( (NMD − μ) / σ ), p_year = 1 − (1 − p_month)^12
μ and σ are the mean and sample standard deviation of the 12 months. Low < 10% a year, moderate < 30%, high otherwise.

Assumptions

  • The next 12 months look like the last 12, scaled by the load growth you enter.
  • Both capacity charges are billed per kVA on the annual utilised capacity. Check your tariff: some municipal tariffs bill the NMD itself, or bill kVA differently.
  • Excess charges follow the Eskom-style rule above with the deadband and forgiven count you set; switch them off for tariffs without them.
  • The risk indicator treats months as independent draws from a normal distribution. Twelve points and seasonal peaks make it a rough guide, not a forecast.
  • Network charges usually depend on supply voltage and distance from the transmission network; use the rates for your supply point.
  • No connection charges or changes to other tariff components are included.

Sources

More technical tools

All technical tools
  • Technical

    Power-factor correction sizing

    Size a capacitor bank from kW and power factor, and see the kVA reduction, demand-charge saving and payback.

    You need
    kW at maximum demand, power factor now and target, R/kVA demand charge
    You get
    kvar required, bank size, kVA and current reduction, saving, payback
    Open the tool
  • Technical

    Load factor and time-of-use profile analyser

    From kWh by time-of-use period and the maximum demand, find the load factor, peak share, all-in cost per kWh and the value of shifting load out of peak.

    You need
    Peak, standard and off-peak kWh, maximum demand, c/kWh rates
    You get
    Load factor, TOU split, c/kWh, saving from load shifting
    Open the tool
  • Technical

    Solar PV yield and self-consumption estimator

    Estimate generation for a South African city from typical specific yields, then split it into self-consumed and exported energy and value both.

    You need
    System size (kWp), city or specific yield, self-consumption share, tariff
    You get
    Annual kWh, self-consumption and export, savings, payback, NPV
    Open the tool

Also for finance, commercial and investment people: Business case, Solar PPA project finance and more.