Business case: combine tool results into one project

Each technical tool answers one question. This page puts their answers side by side: add a result from any tool as a measure, and see what the whole set costs, saves and returns.

Loading your project…

Method

Cash flow of each measure
CF₀ = −capex CFₜ = S × (1 − d)^(t−1) × (1 + e)^(t−1) − O × (1 + e)^(t−1), t = 1 … n
S = year-1 rand saving (all tariff components), d = yearly fall in the saving (e.g. solar degradation), e = escalation, O = year-1 change in running costs, n = life rounded to whole years.
Simple payback
Payback = capex ÷ (S − O)
Not reached when the running cost is at least the saving.
NPV and IRR
NPV = Σ CFₜ ÷ (1 + r)^t, IRR: the r at which NPV = 0
The portfolio's cash flow is the sum of the measures' by year, so its NPV is the sum of their NPVs. Same functions as every financial tool on the site.
Levelised cost of saved energy
LCSE = (capex × CRF(r, n) + O) ÷ kWh saved a year CRF(r, n) = r (1 + r)^n ÷ ((1 + r)^n − 1)
Only for measures that save kWh. Compare it with the energy rate the measure avoids.
Cost curve (MACC)
Bars sorted by LCSE; bar width = kWh saved a year; height = LCSE
The dashed line is the energy-charge saving ÷ kWh across the bars: the average energy rate avoided.

Assumptions

  • Savings start in year 1 whatever the implementation time, and stop at the end of each measure's life; nothing is replaced or re-invested.
  • One escalation rate applies to savings and to running costs. That is cautious on running costs (they usually rise with inflation, below tariff increases), so a measure's NPV here can differ slightly from its own tool's.
  • Nominal rand, before tax, with no debt. For tax and section 12L, open the totals in the efficiency tool.
  • Measures are added as entered. Two measures on the same system (for example power-factor correction and a battery, which both cut the billed kVA) may overlap; v1 warns and leaves the netting to you.
  • Demand-only measures (no kWh saved) have payback, NPV and IRR but no cost per kWh, so they sit outside the cost curve.
  • Data tags: a tool's outputs are calculated; a default the tools supplied is assumed; a figure you typed is estimated. If every input of a tool was left at its example values, its saving is tagged assumed. A measure takes the weakest tag among its numbers.
  • The project file is plain JSON with a format name and version number. A file from a newer version of the tools is refused with a message rather than half-read.

Sources

More financial tools

All financial tools
  • FinancialExcel model

    Solar PPA project-finance calculator

    A 1 MWp rooftop plant financed with senior debt: generation, PPA revenue, tax losses and the cash-flow waterfall, with returns, DSCR, LCOE and sensitivity.

    You need
    Plant size and yield, capex, opex, PPA tariff, debt terms, tax
    You get
    Project and equity IRR, DSCR, NPV, LCOE, payback, tornado
    Open the tool
  • FinancialExcel model

    Efficiency upgrade and section 12L calculator

    The after-tax business case for an efficiency investment, with and without the section 12L allowance: NPV, IRR, payback and sensitivity.

    You need
    Capex, kWh saved, tariff, maintenance, tax rate, 12L rate
    You get
    NPV and IRR with and without 12L, payback, tornado
    Open the tool
  • Financial

    Levelised cost of energy (LCOE) calculator

    The constant price per kWh that recovers capex and O&M over the life, in real and nominal terms, with a capex/O&M split.

    You need
    Capacity, capex, O&M, capacity factor, life, discount rate, inflation
    You get
    Real and nominal LCOE, PV of costs and energy, CRF check
    Open the tool

Also for engineers and facility managers: NMD optimiser, Power-factor correction and more.